Crane works completed on the Tower at White City

August 2018

This 450 tonne mobile crane with fly-jib configuration came down this week. The crane installed approximately 7 cladding panels a day, working 7 days a week, on the 35 storey tower. This 18 day operation was completed successfully on the 13th of August 2018. Progress is going well on all fronts with the development of the White City Campus Tower.